CARINITY BROWNESHOLME

DARLING DOWNS WEST, TOOWOOMBA

Contractor

Paynters

Project Value

$28 million

Project Scope

4,600sqm of suspended slab

Start Date

April 2020

Finish Date

November 2020

This retirement project consisted of large concrete columns and just under 5,000m2 of suspended slab.

The largest pour was 2,200m2. We also poured just under 600m3 in one pour using three concrete pumps.