AURA THE NINTH

MIDDLE RIDGE, TOOWOOMBA

Contractor

McNab

Project Value

$37 million

Project Scope

11,900sqm of suspended slab

Start Date

September 2021

Finish Date

June 2022

This large, multilevel project consisted of three towers, 180 concrete columns, and 12,000m2 of suspended slab along with concrete stairs and walls.

TFC partner company Darkstone worked alongside us on this project achieving over 20,000m2 of concrete over a 6mth period.